India Project Import Regulations: court confirms project-import exemption can cover post-registration consignments

Key facts5

  • In Vatech Wabag Limited v. Assistant Commissioner of Customs, the Madras High Court partly allowed a challenge to Customs proceedings dated 2 June 2026 that had denied assessment under Heading 98.01 of the Customs Tariff Act, 1975 and the Project Import Regulations, 1986.
  • The case concerned equipment for a 400 MLD seawater reverse-osmosis desalination plant at Perur, awarded by the Chennai Metropolitan Water Supply and Sewerage Board; Vatech Wabag imported five consignments of fasteners and a filter cartridge under Bills of Entry dated 30 October 2024, 8 February 2025, 19 March 2025, and 13 August 2025 (two consignments).
  • The project contract was registered with Customs on 5 June 2025, while the imported goods had been cleared on payment of 15% customs duty.
  • The High Court held that the date of a purchase order placed with a foreign supplier is not the date of importation for Project Import Regulations eligibility; Customs could not deny the Heading 98.01 benefit solely because purchase orders predated project-contract registration.
  • The ruling supports project-import treatment for consignments imported after the 5 June 2025 registration date, notwithstanding earlier purchase orders, as reported on 11 October 2026.

Trade impact3

  • Importers using India’s project-import procedure should distinguish the purchase-order date from the Bill of Entry/import date when assessing eligibility for Heading 98.01 concessions.
  • For project consignments imported after contract registration, review any denial or duty payment based solely on a pre-registration purchase order and preserve the contract-registration certificate, Bills of Entry, purchase orders, and project-use evidence.
  • For phased projects, ensure project contracts are registered with Customs before later consignments are imported and verify whether post-registration entries qualify for reassessment or refund procedures.

The headline and summary of this briefing were written by AI from the coverage below. They may contain errors, so please check the original articles and the law for anything important. This is general information, not legal or customs advice.

Coverage1

  1. TaxCorp AIOct 11

    Purchase Order Date Is Not the Date of Importation: Madras HC Upholds Project Import Benefit for Post-Registration Consignments

Headlines, excerpts and images are what each publisher shares as its link preview. Selecting one opens the publisher's page. Publishers and rights holders: to have a preview removed, write to contact@kustomsflow.com

How this story developed

  1. Aug 29India court confirms anti-dumping exemption for COREX technology equivalent to blast furnaces
  2. Sep 10India court confirms broad nexus standard for Target Plus duty-exemption claims
  3. Sep 25India court confirms customs can recover differential duty without challenging self-assessment
  4. Oct 12India Project Import Regulations: court confirms project-import exemption can cover post-registration consignments